Project Location
The intersection of 32 Street and Crystal Shores Road in Okotoks will be the site of upcoming utility connection work.
Type of Work
Developer Lamont Land is leading the project, which involves connecting the sanitary trunk main, installing a new manhole, and repaving the road to its existing condition.
Schedule
The work is set to begin on October 22, 2026, and is expected to be completed by October 27, 2026. Crews will work from 7 a.m. to 7 p.m. each day.
Impacts
Residents can expect significant delays and disruptions to traffic flow through the intersection. The following restrictions will be in place:
- No southbound access on 32 Street at Crystal Shores Road
- No left turn onto Crystal Green Way
- No left turn onto Crystal Shores Road via northbound 32 Street
- No westbound access to Crystal Shores Road via Crystal Green Way
To minimize delays, motorists are advised to follow alternate routes. Digital message boards, traffic-control measures, and construction signage will be used to guide drivers and pedestrians through the area. Reduced speeds will be in effect near the construction zone, and traffic and pedestrian detours may remain in place 24 hours a day as needed.
What to Expect
Travelers can expect major delays, increased noise, and temporary changes to traffic patterns and pedestrian routes. Construction crews, heavy equipment, and flag people will be present in the area.
Why This Work is Happening
The work is necessary to extend the existing sanitary trunk main and connect the first phase of the Ridgemont subdivision to the Town’s sanitary service.